Mainnet Beta: Matcha v6 network upgrade
Scheduled·Under maintenance·Oct 27, 1:00 PM - Nov 3, 2:00 PM

The updated Mainnet Beta v6 upgrade timeline is tentatively as follows:

  • Monday 27th October: Cut celestia-app v6.1.x and celestia-node v0.28.x Mainnet Beta releases

  • Tuesday 28th October: Announce Mainnet Beta upgrade to all

  • Tuesday 28th - Sunday 2nd November: Signaling period for v6

  • Monday 3rd November: [TBD] Submit MsgTryUpgrade for v6

  • Monday 10th November: [TBD] v6 activates on Mainnet Beta

Wed, Oct 22, 2025, 01:55 PM
(1 day ago)
·
Affected components
Mainnet Beta
Updates

Scheduled

The updated Mainnet Beta v6 upgrade timeline is tentatively as follows:

  • Monday 27th October: Cut celestia-app v6.1.x and celestia-node v0.28.x Mainnet Beta releases

  • Tuesday 28th October: Announce Mainnet Beta upgrade to all

  • Tuesday 28th - Sunday 2nd November: Signaling period for v6

  • Monday 3rd November: [TBD] Submit MsgTryUpgrade for v6

  • Monday 10th November: [TBD] v6 activates on Mainnet Beta

Wed, Oct 22, 2025, 01:55 PM

Scheduled

The updated Mainnet Beta v6 upgrade timeline is tentatively as follows:

  • Wednesday 22nd October: Cut celestia-app v6.1.x and celestia-node v0.28.x Mainnet Beta releases

  • Thursday 23rd October: Announce Mainnet Beta upgrade to all

  • Thursday 23rd - Monday 27th October: Signaling period for v6

  • Tuesday 28th October: [TBD] Submit MsgTryUpgrade for v6

  • Tuesday 4th November: [TBD] v6 activates on Mainnet Beta

Tue, Oct 14, 2025, 04:23 PM(1 week earlier)

Scheduled

The tentative schedule for Mainnet Beta upgrade to v6 Matcha is:

  • Wednesday 15th October: Cut celestia-app v6.1.1 and celestia-node v.0.28.0 Mainnet Beta releases

  • Thursday 16th October: Announce Mainnet Beta upgrade to all

  • Thursday 16th - Monday 20th October: Signaling period for v6

  • Tuesday 21st October: [TBD] Submit MsgTryUpgrade for v6

  • Tuesday 28th October: [TBD] v6 activates on Mainnet Beta

Fri, Oct 10, 2025, 04:09 PM(4 days earlier)